In addition to the 2026 work, in 2025 Ramsey County will complete a stormwater improvement project on Hamline at Clarmar Lane. The construction timeline and communications about impacts to the traveling public will be available on Ramsey County’s project webpage. Although the 2026 projects will coordinate with the 2025 project, the scope of the projects made sense for the drainage project to take place first.
Public Engagement
The first Neighborhood Meeting was held May 1, 2025. Another meeting will be held in the fall when more design details are known. In the meantime, please contact staff with any comments or questions. Empty heading
Funding
The project costs will be funded with a combination of funds from all three agencies – City of Roseville, City of Arden Hills, and Ramsey County. Arden Hills and Roseville’s Municipal State Aid funds (gas tax) and County funds will be used to fund construction of the pathways. Ramsey County will pay for the resurfacing of the roadway and their portion of pathway costs with Wheelage Tax and Regional Sales Tax funds. Watermain improvements will be paid with Arden Hills and Roseville utility funds (utility fees). There will be no assessments to property owners for these improvements.
Schedule
Council Actions are denoted with CC. Public Works, Environment and Transportation Commission items are denoted as PWET. CC and PWET meetings are open to the public and are also available for viewing on the Roseville website or Channel 16 for cable subscribers.
Summer 2025 – Preliminary Design
Winter 2025 – Final Design and project bidding
Summer 2026 – Construction
Please note, this schedule is subject to change.