Twin Lakes Trail Project

NightTrail

Overview 


In 2021, the City of Roseville completed Phase 1 of the Twin Lakes Trail. The new 10 foot bituminous trail runs over former Ramsey County Ditch 4 (RCD 4) from County Road C to Terrace Avenue. The new trail was opened in October 2021.

In 2023, the City plans to construct Phase 2 of the Twin Lakes Trail, extending the trail from Terrace Drive into Oasis Park completing the trail improvements. Similar to Phase 1, the new bituminous trail will include lighting, benches and landscaping. 

The construction of the trail will be paid for by the City of Roseville with funds acquired from recent developments.  As a result, there will be no cost or assessment to property owners.  Construction of the proposed pathway will begin during the summer of 2023 and should be open for public use by September 2023.

Twin Lakes Trail Map

Past Meetings


A neighborhood meeting was held virtually on Monday December 17. A copy of the presentation can be found here.

A second neighborhood meeting was held virtually on Monday, December 21. A copy of the presentation can be found here.

A third neighborhood meeting was held on Thursday, June 3 at 6:00 pm at Oasis Park. The meeting discuss the proposed project for Phase 2 of the Twin Lakes Trail including review of the updated feasibility report

At the July 12, 2021 City Council Meeting, the Council approved moving forward with Phase 2 final plans to make the connection from Terrace Drive into Oasis Park.  Construction on Phase 2 will begin in the summer of 2023.

Related Projects


RCD 4 Project  Additional information on the storm sewer project can be found on the RCD 4 Project webpage.

Schedule


All work on Phase 1 is completed other than benches and trash receptacles, which will be added later this summer.  Work on Phase 2 is expected to begin in the fall of 2023.