2023 Pathway Project

Marion Street; Lexington and Cleveland Avenues

Overview 

The City of Roseville, in cooperation with Ramsey County, will be constructing pathways on Marion Street between Larpenteur Avenue and the end of the cul-de-sac; Lexington Avenue between Hwy 36 and County Road B2; and on Cleveland Avenue from Iona Lane extending north 600 feet.  These segments will fill in a gap in the pathway network and provide pathway access to Unity Park.  Additionally, Marion Street cul-de-sac will have a lift of pavement milled and newly paved. The pathways will be constructed in the summer of 2023. Funding for the project is provided by Community Development Block Grant, City Municipal State Aid Funds, County State Aid Funds and local street funds.  

There will be no assessments to adjacent property owners. 

Meetings

A Lexington Avenue pathway neighborhood meeting was held on Thursday, November 3, 2022. Link to the presentation is on the right.

Schedule

More schedule information will be posted once a contractor has been selected for this project.

Spring 2023 – Open Bids/Award Contract

Summer 2023 – Construction